Flood Control and Drainage17PD0027No coordinates published by DPWH

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF CONNECTION OF SEWERLINE FROM PUROK 1 TO RIMANDO ROAD, WEST MODERNSITE, BAGUIO CITY, BENGUET

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF CONNECTION OF SEWERLINE FROM PUROK 1 TO RIMANDO ROAD, WEST MODERNSITE, BAGUIO CITY, BENGUET is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱1,631,632.95. Status: Reported complete (DPWH). Contractor on record: 4RMCONSTRUCTION. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region

DPWH did not publish coordinates for this project. Location estimated from the project title (town level only); satellite images may not show the exact site.

Region: Cordillera Administrative Region

No before/after satellite images: DPWH did not publish coordinates, and the location estimated from the project title is only town level, which is not confident enough to image.

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱2,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROX-17-0025803 · ₱6,505,000 · release to the district office, not itemized per project

    Possible match · score 0.59

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17PD0027 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF CONNECTION OF SEWERLINE FROM PUROK 1 TO RIMANDO ROAD, WEST MODERNSITE, BAGUIO CITY, BENGUET

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Sagudin River, Brookside, Baguio City, Benguet
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-17-0025803

₱6,505,000.00 · FY2017

Released to Northern Mindanao Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

17 projects · ₱174.1M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM-PAVING OF UNPAVED ROADS-TERTIARY ROADS JCT. TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD ROAD. CHAINAGE 4,685-CHAINAGE 5,275

Mountain Province 2nd DEO, Cordillera Administrative Region

2020₱22.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - (S04030LZ) CHAINAGE 3415 - CHAINAGE 4015

Mountain Province 2nd DEO, Cordillera Administrative Region

2022₱21.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-PAVING OF UNPAVED ROADS - TERTIARY ROADS, JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - (S04030LZ) CHAINAGE 4015 - CHAINAGE 4685

Mountain Province 2nd DEO, Cordillera Administrative Region

2021₱19.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BESAO-TUBO (VIA TAMBOAN) ROAD, MT. PROVINCE SECTION, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2020₱19.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - SPECIFIC LOCATION ALONG CITY LIMIT - STO. TOMAS ROAD (S00404LZ), K0262+532 - K0263+412, TUBA, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2020₱16.2M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY RDS, AGOO-BAGUIO CITY RD, K0240+934-K0241+234, TUBAO, LU

La Union 2nd DEO, Region I

2023₱14.5M
Reported complete (DPWH)
View all 17 projects →

4. Implementation

Contract Amount

₱1,631,632.95

Progress

Reported complete (DPWH)

Start Date

April 30, 2017

Target End

June 24, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.