Pattern Consistent with Contract Splitting
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 3 contracts awarded to RS RODRIGUEZ CONST & SUPPLIES / JHI CONST & SUPPLY by the same office started within 0 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 3 in the same municipality. It is common for large flood control projects to be split into several contracts covering different barangays or sections for logistical or administrative reasons.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure along Banila River, Barangay La Paz -San Leon, Umingan, Pangasinan (Package 1)22AI0060 | 100% | September 30, 2022 | October 10, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: March 23, 2022 · Source fetched October 21, 2026
Rule Definition
≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold with similar scope
{
"deo": "Pangasinan 3rd District Engineering Office",
"contractId": "22AI0060",
"contractor": "RS RODRIGUEZ CONST & SUPPLIES / JHI CONST & SUPPLY",
"windowDays": 120,
"clusterSize": 3,
"thresholdPhp": 50000000,
"contractCostPhp": 48958847.19,
"averageTitleSimilarity": 0.9615638644328854
}Source documents
Possible Innocent Explanations
- Legitimate multi-lot procurement
- Different sites under same program