Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24EH0081 was awarded at 100.00% of its ABC. Across its 67 recorded contracts, SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP was awarded at ≥99.5% of ABC 61 times (91.0%), versus 70.4% for flood-control contracts overall. It is possible that competitive bidding led to a bid exactly matching the ABC, or that the ABC was set with high precision.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Mainit (DS - RS ) Flood Control Structure, Odiongan, Romblon24EH0081Flood control | 100% | March 7, 2025 | September 23, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: March 13, 2024 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Romblon District Engineering Office",
"ratio": 1.000000003573343,
"abcPhp": 139924999.5,
"threshold": 0.995,
"contractId": "24EH0081",
"contractor": "SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP",
"contractCostPhp": 139925000
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
