Schedule / Date Anomalies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23AI0091 (₱14.51M) is recorded as completed in 27 days against 128 planned; similar-cost projects take a median of 182 days, putting it in the fastest 0.2%. This could be due to unusually efficient work, pre-fabrication, or favorable site conditions.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure Located at Barangay San Joaquin, Balungao, Pangasinan23AI0091Flood control | 100% | August 6, 2023 | April 27, 2023 | — | completedsumbong source |
Start: March 31, 2023 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2023-03-31T00:00:00.000Z",
"contractId": "23AI0091",
"actualEndDate": "2023-04-27T00:00:00.000Z",
"targetEndDate": "2023-08-05T00:00:00.000Z",
"contractCostPhp": 14509105.66
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo