Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24CF0026 (₱94.57M) is recorded as completed in 77 days against 293 planned; similar-cost projects take a median of 285 days, putting it in the fastest 2.2%. The project may have benefited from unusually favorable conditions or efficient management.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure along Peñaranda River, Barangay San Nicolas, Gapan City, Nueva Ecija24CF0026Flood control | 100% | January 20, 2025 | June 18, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: April 2, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-04-02T00:00:00.000Z",
"contractId": "24CF0026",
"actualEndDate": "2024-06-18T00:00:00.000Z",
"targetEndDate": "2025-01-19T00:00:00.000Z",
"contractCostPhp": 94569740.12
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
Cite this record
Love the Philippines. “Schedule / Date Inconsistencies (C4): Construction of Flood Control Structure along Peñaranda River, Barangay San Nicolas, Gapan City, Nueva Ecija.” Source: sumbong. Data as of October 21, 2026. https://lovethephilippines.com/risk/266faed8-f360-40a9-aec8-1716a20dff6d
The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.