Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24AI0245 (₱86.67M) is recorded as completed in 48 days against 267 planned; similar-cost projects take a median of 285 days, putting it in the fastest 0.5%. This could be due to early completion reporting, pre-existing work, or rapid mobilization.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure along Tagamusing and Allied Rivers, Package 2, Pozorrubio, Pangasinan24AI0245 | 100% | March 1, 2025 | July 25, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: June 7, 2024 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2024-06-07T00:00:00.000Z",
"contractId": "24AI0245",
"actualEndDate": "2024-07-25T00:00:00.000Z",
"targetEndDate": "2025-02-28T00:00:00.000Z",
"contractCostPhp": 86674471.29
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
- This could be due to early completion reporting, pre-existing work, or rapid mobilization.