Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23AI0011 (₱48.90M) is recorded as completed in 46 days against 200 planned; similar-cost projects take a median of 239 days, putting it in the fastest 0.7%. The contractor may have deployed unusually large resources or worked in parallel to finish ahead of schedule.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure along Tagamusing and Allied River, Sta. 0+000 - Sta. 0+296, Binalonan, Pangasinan (Package 13)23AI0011 | 100% | August 29, 2023 | March 28, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: February 10, 2023 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2023-02-10T00:00:00.000Z",
"contractId": "23AI0011",
"actualEndDate": "2023-03-28T00:00:00.000Z",
"targetEndDate": "2023-08-28T00:00:00.000Z",
"contractCostPhp": 48895892.15
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
Cite this record
Love the Philippines. “Schedule / Date Inconsistencies (C4): Construction of Flood Control Structure along Tagamusing and Allied River, Sta. 0+000 - Sta. 0+296, Binalonan, Pangasinan (Package 13).” Source: sumbong. Data as of October 21, 2026. https://lovethephilippines.com/risk/3ece6ad3-baec-4f94-8ca9-38e039822583
The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.