Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 23CD0018 was awarded at 100.00% of its ABC. Across its 21 recorded contracts, YPR GEN CONTRACTOR AND CONST SUPPLY INC was awarded at ≥99.5% of ABC 20 times (95.2%), versus 70.4% for flood-control contracts overall. This may be due to highly competitive bidding where the winning bid matches the ABC exactly.

Public record entityConstruction of Flood Control Structure along Angat River, Santa Lucia, Angat, Bulacan
LocationANGAT (BULACAN), BULACAN, Region IIIContract 23CD0018
Amount₱33,174,759.59100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structure along Angat River, Santa Lucia, Angat, Bulacan23CD0018Flood control100%September 3, 2023August 2, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: February 22, 2023 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Bulacan 2nd District Engineering Office",
  "ratio": 1.0000040775141474,
  "abcPhp": 33174624.32,
  "threshold": 0.995,
  "contractId": "23CD0018",
  "contractor": "YPR GEN CONTRACTOR AND CONST SUPPLY INC",
  "contractCostPhp": 33174759.59
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate
  • This may be due to highly competitive bidding where the winning bid matches the ABC exactly.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)BulacanAngatSanta Lucia
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Kajiki 2025Man-Yi 2024
Hazard exposure
Active fault16.1 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)outside mapped flood zonesUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgenot inundated even at SSA4 (>5 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.