Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 25OE0081 (₱37.96M) is recorded as completed in 39 days against 39 planned; similar-cost projects take a median of 239 days, putting it in the fastest 0.5%. The project may have involved pre-fabricated components or unusually efficient work scheduling.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Installation of Booster Pump (Accessories) along Estero dela Reina, Manila City (Phase II)25OE0081Flood control | 100% | April 20, 2025 | April 20, 2025 | — | completedsumbong source |
Start: March 12, 2025 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2025-03-12T00:00:00.000Z",
"contractId": "25OE0081",
"actualEndDate": "2025-04-20T00:00:00.000Z",
"targetEndDate": "2025-04-19T00:00:00.000Z",
"contractCostPhp": 37962740.47
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo