Cross-Source Mismatch (PhilGEPS vs DPWH)
Linked PhilGEPS award amount or awardee disagrees with Sumbong contract row.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: PhilGEPS award 22EA0243 lists ₱22.48M to JEDIDIAH CONSTRUCTION, while DPWH records contract 22EA0243 at ₱24.73M to JEDIDIAH CONST. The contract amount may have increased after the initial award due to approved variation orders or additional scope.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Sumangga Flood Control Structure, Mogpog, Marinduque22EA0243Flood control | 100% | February 10, 2023 | February 10, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: March 30, 2022 · Source fetched October 21, 2026
Rule Definition
Compares linked award and project contractor/cost above tolerance.
Triggering Data & citations
Linked PhilGEPS award fields disagree with DPWH/Sumbong contract record
{
"linkId": "62f1e017-60c1-425c-b281-75a367577dd1",
"awardId": "bc499b11-3164-4267-b2cb-72157c48ff02",
"linkScore": 1,
"nameMismatch": false,
"amountMismatch": true,
"awardAmountPhp": 22481783.64,
"linkValidation": "philgeps_ref equals DPWH contract ID",
"projectCostPhp": 24729962.75,
"philgepsAwardee": "JEDIDIAH CONSTRUCTION"
}Source documents