Duplicate or Near-Duplicate Projects
Very similar descriptions within ~100m or identical coordinates across contracts/years.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contracts 24CE0195 and 23CE0185 have near-identical descriptions about 149 m apart (funding years 2023, 2024; ₱4.90M, ₱4.90M). Worth checking whether they cover the same works. It is possible that the second project is a continuation or expansion of the first, or that additional structures were needed in the same area.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structures along Casongsong River, Brgy. Casongsong, Guimba, Nueva Ecija23CE0185Flood control | 100% | August 5, 2023 | July 27, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: June 7, 2023 · Source fetched October 21, 2026
Rule Definition
Title similarity + distance or shared coordinates within municipality.
Triggering Data & citations
Similar project description near another contract in the same municipality
{
"contractId": "23CE0185",
"coordinates": {
"lat": 15.673295,
"lon": 120.74669
},
"municipality": "GUIMBA (NUEVA ECIJA)",
"distanceMeters": 149.1445606849712,
"titleSimilarity": 1
}Source documents