Schedule / Date Anomalies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24AG0013 (₱96.50M) is recorded as completed in 71 days against 295 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.7%. The contractor may have deployed unusually large resources or worked in optimal conditions, allowing for rapid completion.

Public record entityConstruction of Flood Mitigation Structure along Balingcaguing River (Caranglaan Section), Sta. 017+829 - Sta. 018+229, Barangay Caranglaan, Mabini, Pangasinan
LocationMABINI (PANGASINAN), PANGASINAN, Region IContract 24AG0013
Amount₱96,500,000.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0

Start: February 12, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-02-12T00:00:00.000Z",
  "contractId": "24AG0013",
  "actualEndDate": "2024-04-23T00:00:00.000Z",
  "targetEndDate": "2024-12-02T00:00:00.000Z",
  "contractCostPhp": 96500000
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo