Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 22CC0236 was awarded at 100.00% of its ABC. Across its 20 recorded contracts, A R L CONST was awarded at ≥99.5% of ABC 19 times (95.0%), versus 70.4% for flood-control contracts overall. It is possible that the contractor consistently bids close to the ABC to maximize their chances of winning within legal limits.

Public record entityConstruction of Major River System, Angat River, Culianin and Makinabang Section, Sta. 00 + 632 to Sta. 01 + 007, Plaridel/Baliwag, Bulacan
LocationCITY OF BALIUAG (BULACAN), BULACAN, Region IIIContract 22CC0236
Amount₱95,534,903.44100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Major River System, Angat River, Culianin and Makinabang Section, Sta. 00 + 632 to Sta. 01 + 007, Plaridel/Baliwag, Bulacan22CC0236Flood control100%February 27, 2023December 12, 2022—completedsumbong source

Start: April 4, 2022 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Bulacan 1st District Engineering Office",
  "ratio": 0.9999996606477022,
  "abcPhp": 95534935.86,
  "threshold": 0.995,
  "contractId": "22CC0236",
  "contractor": "A R L CONST",
  "contractCostPhp": 95534903.44
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate