Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 23E00030 was awarded at 100.00% of its ABC. Across its 67 recorded contracts, SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP was awarded at ≥99.5% of ABC 61 times (91.0%), versus 70.4% for flood-control contracts overall. It is possible that the contractor consistently bids at or just below the ABC to maximize their chances of winning within legal limits.

Public record entityConstruction of Road Dike/Esplanade along Patrick River, Sablayan, Occidental Mindoro
LocationSABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-BContract 23E00030
Amount₱217,123,574.40100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Road Dike/Esplanade along Patrick River, Sablayan, Occidental Mindoro23E00030Flood control100%March 26, 2024December 15, 2023—completedsumbong source

Start: February 11, 2023 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Mindoro Occidental District Engineering Office",
  "ratio": 0.9999934719629083,
  "abcPhp": 217124991.8,
  "threshold": 0.995,
  "contractId": "23E00030",
  "contractor": "SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP",
  "contractCostPhp": 217123574.4
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate