Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 23AJ0003 (₱19.60M) is recorded as completed in 26 days against 162 planned; similar-cost projects take a median of 182 days, putting it in the fastest 0.2%. The contractor may have deployed unusually large resources or worked in parallel to finish the project quickly.

Public record entityConstruction of Slope Protection Works along Marusay River, Poblacion East, Calasiao, Pangasinan
LocationCALASIAO (PANGASINAN), PANGASINAN, Region IContract 23AJ0003
Amount₱19,599,931.81 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Slope Protection Works along Marusay River, Poblacion East, Calasiao, Pangasinan23AJ0003Flood control100%November 30, 2023July 17, 2023—completedsumbong source

Start: June 21, 2023 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2023-06-21T00:00:00.000Z",
  "contractId": "23AJ0003",
  "actualEndDate": "2023-07-17T00:00:00.000Z",
  "targetEndDate": "2023-11-29T00:00:00.000Z",
  "contractCostPhp": 19599931.81
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo