Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 22, 2026

High Concurrent Workload for One Contractor

Contractor linked to many simultaneous projects or very high total value vs peers.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: JWU CONST AND SUPPLY holds 33 flood-control contracts worth ₱2.68B, 2.64× the 95th-percentile contractor total (₱1.01B); up to 17 ran at the same time. This is a capacity question worth examining. The contractor may have demonstrated exceptional capacity or specialization in flood-control projects, leading to a higher number of awards.

Public record entityJWU CONST AND SUPPLYOrganization record →
Location—
AmountData not yet available sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 33Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Amobocan, Flood Control Project (Package 1), Amobocan, Cauayan City, Isabela23BH0059Flood control100%October 7, 2023August 22, 2023—completedsumbong source
Construction of Bantay Flood Control Structure, Section 1, Jones, Isabela24BH0210Flood control100%June 19, 2025November 12, 2024—completedsumbong source
Construction of Dammang West Flood Control Structure, Echague, Isabela24BH0113Flood control100%January 3, 2025July 18, 2024—completedsumbong source
Construction of Diarao Flood Control Structure, Section 1, Jones, Isabela24BH0220Flood control100%June 16, 2025December 4, 2024—completedsumbong source
Construction of Flood Control and Drainage Structure Section 2, Barangay Palawan, San Guillermo, Isabela24BH0276Flood control100%September 24, 2025November 30, 2024—completedsumbong source
Construction of Flood Control Structure, Barangay Saranay, Cabatuan, Isabela24BG0118Flood control100%April 26, 2025August 8, 2024—completedsumbong source
Show 27 more projects in this bucket
Construction of Flood Control Structure, Baringin Section 2, Cauayan City, Isabela23BH0194Flood control100%March 28, 2024March 5, 2024—completedsumbong source
Construction of Flood Control Structure, Brgy. Cassap Fuera, Cauayan City, Isabela23BH0190Flood control100%April 2, 2024August 30, 2023—completedsumbong source
Construction of Flood Control Structure, Brgy. Nagcampegan, Cauayan City, Isabela23BH0188Flood control100%February 15, 2024December 11, 2023—completedsumbong source
Construction of Flood Control Structure, Brgy. San Pablo, Cauayan City, Isabela23BH0187Flood control100%March 29, 2024October 6, 2023—completedsumbong source
Construction of Flood Control Structure, Brgy. Sinnipil, Cauayan City, Isabela23BH0189Flood control100%February 15, 2024August 30, 2023—completedsumbong source
Construction of Flood Control Struture, Barangay Tupax, Jones, Isabela24BH0159Flood control100%March 31, 2025December 4, 2024—completedsumbong source
Construction of Flood Control System, Barangay Carabatan Chica, Cauayan City, Isabela22BH0123Flood control100%September 27, 2022September 27, 2022—completedsumbong source
Construction of Mallig River Flood Control Project, Barangay Imbiao Phase II, Sta. 0+960 - Sta. 1+760, Roxas, Isabela24BF0061Flood control100%April 16, 2025February 10, 2025—completedsumbong source
Construction of Mallig River Flood Control Project, Barangay San Juan, Quirino, Isabela Sta Sta 0 + 000 - Sta 0 + 38824BF0003Flood control100%September 25, 2024June 24, 2024—completedsumbong source
Construction of Masaya Sur Flood Control Structure, Section 1, barangay Masaya Sur, San Agustin, Isabela24BH0193Flood control100%May 26, 2025August 1, 2024—completedsumbong source
Construction of Pinacanauan River Flood Control Project, Barangay Maluno, Sta. 0+000 - Sta. 0+722, Benito Soliven, Isabela24BG0175Flood control100%April 20, 2025October 15, 2024—completedsumbong source
Construction of Pongpongan Flood Control Structure, Section 1, Jones, Isabela24BH0186Flood control100%June 12, 2025November 12, 2024—completedsumbong source
Construction of Siffu River Flood Control Project (Barangay Simimbaan Phase II), Sta. 0+960 - Sta. 1+760, Roxas, Isabela24BF0001Flood control100%February 3, 2025April 6, 2024—completedsumbong source
Construction of Siffu River Flood Control Project (Masigun Section), Roxas, Isabela23BF0017Flood control100%November 18, 2023July 2, 2023—completedsumbong source
Construction of Siffu River Flood Control Project, Barangay San Juan Phase II, Sta. 0+600 - Sta. 1+400, Quirino, Isabela24BF0053Flood control100%April 13, 2025August 14, 2024—completedsumbong source
Construction of Siffu River Flood Control Project, Barangay Suerte Phase III, Sta. 0+400 - Sta. 1+200, Quirino, Isabela24BF0055Flood control100%March 19, 2025May 6, 2024—completedsumbong source
Construction River Flood Control Project along Ganano River Bank, barangay Apanay, Alicia, Isabela23BG0042Flood control100%September 16, 2023June 1, 2023—completedsumbong source
Construction of Cagayan River Flood Control Project at Barangay Minanga, Naguilian, Isabela24BG0070100%February 20, 2025August 5, 2024—completedsumbong source
Construction of Cagayan River Flood Control Project, Brgy. San Guillermo (Phase II), Angadanan, Isabela24BG0007100%May 10, 2025December 17, 2024—completedsumbong source
Construction of Flood Control Structure, Barangay Paraiso, Cabatuan, Isabela24BG0006100%January 23, 2025June 20, 2024—completedsumbong source
Construction of Ganano River Flood Control Project, Barangay Apanay (Sta 0 + 000 - Sta 0 + 188.30), Alicia, Isabela24BG0231100%March 25, 2025October 25, 2024—completedsumbong source
Construction of Ganano River Flood Control Project, Barangay Apanay Downstream (Sta. 0+000 - Sta. 0+470.40), Alicia, Isabela24BG0089100%May 13, 2025September 27, 2024—completedsumbong source
Construction of River Flood Control Project along Ganano River Bank, Barangay San Antonio Upstream (Sta. 0+000 - Sta. 0+067.90, Sta. 0+070.90 - Sta. 0+465.60), Alicia, Isabela24BG0069100%May 17, 2025August 5, 2024—completedsumbong source
Construction of River Flood Control Project along Ganano River Bank, Barangay San Antonio Upstream (Sta. 0+465.50 - Sta. 0+928.20), Alicia, Isabela24BG0068100%May 17, 2025August 5, 2024—completedsumbong source
Construction of River Flood Control Project along Ganano River Bank, Barangay Sta. Maria (Sta. 0+000 - Sta. 0+468.30), Alicia, Isabela24BG0091100%May 13, 2025October 25, 2024—completedsumbong source
Construction of Slope Protection Structure for Cagayan River Basin, Magat River, Aplat Section, Package 2, Aurora, Isabela24BF0044100%August 9, 2025March 21, 2025—completedsumbong source
Construction of Slope Protection Works for Cagayan River Basin, Siffu River, San Placido, Roxas, Isabela24BF0013100%March 9, 2025April 16, 2024—completedsumbong source

Rule Definition

Active project count and total value vs peer 95th percentile.

Triggering Data & citations

Contractor carries far more concurrent flood-control value than peers

{
  "contractor": "JWU CONST AND SUPPLY",
  "projectCount": 33,
  "totalValuePhp": 2678719587.49,
  "peerP95TotalPhp": 1014143494.4100002,
  "activeProjectCount": 0,
  "simultaneousThreshold": 25
}

Possible Innocent Explanations

  • Large national firm with many concurrent government clients
  • Data groups joint ventures under one name