Construction of Flood Mitigation Structure22BH0123

Construction of Flood Control System, Barangay Carabatan Chica, Cauayan City, Isabela

Construction of Flood Control System, Barangay Carabatan Chica, Cauayan City, Isabela is a DPWH-tracked public work in CITY OF CAUAYAN (ISABELA), ISABELA, Region II. Reported contract value: ₱14,834,053.16. Status: Reported complete (DPWH). Contractor on record: JWU CONST AND SUPPLY. Figures trace to sumbong.

CITY OF CAUAYAN (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System, Barangay Carabatan Chica, Cauayan City, Isabela
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-22-0009488

₱807,777.00 · FY2022

Released to Regional Office - XII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002983

₱603,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001961

₱82,188,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0003822

₱2,384,547.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0003823

₱222,968.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

305 projects · ₱13.7B total · 52 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING - TERTIARY ROADS - NAGUILIAN-SAN MARIANO ROAD, ISABELA

Region II, Region II

2023₱169.0M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MIT. FACI. W/IN MAJOR BASINS & PRIN. RIVERS -CONST. OF FLOOD CONT. STRUC. ALONG ARINGAY RIVER BASIN, TUBAO, LA UNION (PACKAGE 8), TUBAO, LA UNION

La Union 2nd DEO, Region I

2025₱144.7M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRU

Isabela 2nd DEO, Region II

2024₱144.7M
Reported complete (DPWH)

Construction of Slope Protection Structure for Cagayan River Basin, Magat River, Aplat Section, Package 2, Aurora, Isabela

AURORA (ISABELA), ISABELA, Region II

2024₱144.7M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PACKAGE 2, GUIBANG,

Isabela 3rd DEO, Region II

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, TALLUNGAN

Isabela 3rd DEO, Region II

2024₱144.7M
Past target date (DPWH On-Going)
View all 305 projects →

4. Implementation

Contract Amount

₱14,834,053.16

Progress

Reported complete (DPWH)

Start Date

April 1, 2022

Target End

September 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.