Construction of Flood Mitigation Structure24BH0193

Construction of Masaya Sur Flood Control Structure, Section 1, barangay Masaya Sur, San Agustin, Isabela

Construction of Masaya Sur Flood Control Structure, Section 1, barangay Masaya Sur, San Agustin, Isabela is a DPWH-tracked public work in SAN AGUSTIN (ISABELA), ISABELA, Region II. Reported contract value: ₱96,477,720.00. Status: Reported complete (DPWH). Contractor on record: JWU CONST AND SUPPLY. Figures trace to sumbong.

SAN AGUSTIN (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱43,008,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Masaya Norte, San Agustin, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010524

₱1,526,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010585

₱141,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

305 projects · ₱13.7B total · 52 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING - TERTIARY ROADS - NAGUILIAN-SAN MARIANO ROAD, ISABELA

Region II, Region II

2023₱169.0M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MIT. FACI. W/IN MAJOR BASINS & PRIN. RIVERS -CONST. OF FLOOD CONT. STRUC. ALONG ARINGAY RIVER BASIN, TUBAO, LA UNION (PACKAGE 8), TUBAO, LA UNION

La Union 2nd DEO, Region I

2025₱144.7M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRU

Isabela 2nd DEO, Region II

2024₱144.7M
Reported complete (DPWH)

Construction of Slope Protection Structure for Cagayan River Basin, Magat River, Aplat Section, Package 2, Aurora, Isabela

AURORA (ISABELA), ISABELA, Region II

2024₱144.7M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PACKAGE 2, GUIBANG,

Isabela 3rd DEO, Region II

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, TALLUNGAN

Isabela 3rd DEO, Region II

2024₱144.7M
Past target date (DPWH On-Going)
View all 305 projects →

4. Implementation

Contract Amount

₱96,477,720.00

Progress

Reported complete (DPWH)

Start Date

May 20, 2024

Target End

May 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.