Construction of Revetment24BG0007

Construction of Cagayan River Flood Control Project, Brgy. San Guillermo (Phase II), Angadanan, Isabela

Construction of Cagayan River Flood Control Project, Brgy. San Guillermo (Phase II), Angadanan, Isabela is a DPWH-tracked public work in ANGADANAN (ISABELA), ISABELA, Region II. Reported contract value: ₱96,479,423.61. Status: Reported complete (DPWH). Contractor on record: JWU CONST AND SUPPLY. Figures trace to sumbong.

ANGADANAN (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Control Project, Barangay San Guillermo ( Phase III ) , Angadanan, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004352

₱1,853,487.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0009805

₱1,459,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0003846

₱276,213.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004354

₱173,574.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010584

₱135,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,479,423.61

Progress

Reported complete (DPWH)

Start Date

June 17, 2024

Target End

May 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.