Contractor Concentration (Flood Control)
A contractor holds a very large share of flood-control contract value in a district or province.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: MG SAMIDAN CONST received 38.5% (₱2.95B of ₱7.65B) of recorded flood-control contract value in Abra District Engineering Office across 105 contracts and 12 contractors, at or above the 25% share threshold (HHI 0.24). This may be due to the contractor's strong track record or specialization in flood-control projects in the area.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
Flagged peer group: Abra District Engineering Office
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Angad Flood Control, Bangued, Abra22PA0329Flood control | 100% | April 28, 2023 | February 3, 2025 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Bañacao Flood Control, Bangued, Abra22PA0331Flood control | 100% | July 2, 2023 | May 4, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Baybayatin Flood Control, Lagayan, Abra23PA0125Flood control | 100% | January 3, 2024 | January 3, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Buli Flood Control Structure, Buli, La Paz, Abra24PA0060Flood control | 100% | September 16, 2024 | September 16, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Cardona Flood Control Structure, Barangay Cardona, Dolores, Abra22PA0362Flood control | 100% | November 25, 2023 | November 25, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Caribot Flood Control Structure, Barangay Mudeng, La Paz, Abra22PA0335Flood control | 100% | July 11, 2023 | June 5, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Show 25 more projects in this bucket
| Construction of Coribot Flood Control Phase 2, Mudeng, La Paz, Abra22PA0336Flood control | 100% | July 11, 2023 | July 11, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Deet-Pudok Flood Control Structure, Tayum, Abra23PA0048Flood control | 100% | January 12, 2024 | June 29, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin (Phase II), Bagalay, Tayum, Abra23PA0019Flood control | 100% | November 16, 2023 | June 28, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin (Phase II), Banacao, Bangued, Abra23PA0020Flood control | 100% | December 16, 2023 | January 2, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin (Phase II), Banglolao - Labon, Bucay, Abra23PA0021Flood control | 100% | January 13, 2024 | January 13, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin (Phase II), Cabaroan, Tayum, Abra23PA0022Flood control | 100% | January 1, 2024 | July 28, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin, Barangay Ampalioc, Luba, Abra23PA0116Flood control | 100% | March 4, 2024 | March 4, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin, Barangay Lagben, Lagangilang, Abra23PA0152Flood control | 100% | June 10, 2024 | March 12, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin, Barangay Nagtupacan, Dolores, Abra23PA0104Flood control | 100% | March 21, 2024 | April 10, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin, Barangay Presentar-Aguet, Lagangilang, Abra23PA0053Flood control | 100% | October 7, 2023 | October 7, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin, Barangay San Jose Sur, Manabo, Abra23PA0253Flood control | 100% | September 12, 2024 | September 12, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin, Paga, Cardona, Dolores, Abra23PA0136Flood control | 100% | January 10, 2024 | January 10, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Abra Major River Basin, Podayan, Patoc, Bucay, Abra23PA0134Flood control | 100% | April 16, 2024 | April 16, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Ikmin River, Maguyepyep, Sallapadan, Abra23PA0070Flood control | 100% | January 15, 2024 | December 7, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Tineg River, Tagaytay, San Juan, Abra23PA0103Flood control | 100% | November 13, 2023 | July 21, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure, Barangay Isit, Dolores, Abra22PA0338Flood control | 100% | October 1, 2023 | January 30, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure, Malabbaga, La Paz, Abra22PA0363Flood control | 100% | November 19, 2023 | November 17, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Isit Flood Control, Dolores, Abra22PA0339Flood control | 100% | May 22, 2023 | May 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Malabbaga Flood Control Structure (Phase III), Sta. 6 + 820 - Sta. 7 + 820, La Paz, Abra22PA0364Flood control | 100% | November 19, 2023 | July 14, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Malabbaga Flood Control Structure, Malabbaga, La Paz, Abra24PA0114Flood control | 100% | October 1, 2024 | September 18, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Paga Flood Control, Dolores, Abra22PA0343Flood control | 100% | June 6, 2023 | January 6, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Pudok Flood Control (Phase 2), Tayum, Abra24PA0042Flood control | 100% | December 3, 2024 | August 19, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Salangsang Flood Control Structure, La Paz, Abra24PA0037Flood control | 100% | November 27, 2024 | September 18, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Sidongan Flood Control Structure, Barangay Luis, La Paz, Abra22PA0344Flood control | 100% | July 20, 2023 | July 11, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Tayum Flood Control Structure, Tayum, Abra23PA0051Flood control | 100% | November 22, 2023 | June 28, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Rule Definition
Share of contract value by contractor within DEO or province; flags top share > 40% or elevated HHI.
Triggering Data & citations
Contractor holds a large share of flood-control contract value in its district/province
{
"hhi": 0.23996352901949952,
"scope": "deo",
"bucketKey": "deo:Abra District Engineering Office",
"contractor": "MG SAMIDAN CONST",
"thresholds": {
"share": 0.25,
"minContracts": 3,
"minBucketContracts": 10
},
"bucketTotalPhp": 7652897214.8,
"contractorShare": 0.3850298499425235,
"contractorTotalPhp": 2946593866.24,
"contractorContracts": 31
}Source documents
Possible Innocent Explanations
- This may be due to the contractor's strong track record or specialization in flood-control projects in the area.