Duplicate or Near-Duplicate Projects
Very similar descriptions within ~100m or identical coordinates across contracts/years.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contracts 24BA0017 and 23BA0002 have near-identical descriptions about 72 m apart (funding years 2023, 2024; ₱9.78M, ₱9.74M). Worth checking whether they cover the same works. It is possible that the second contract is a continuation or second phase of the first project, but the earlier contract did not specify a phase.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Uyugan Flood Control (Valugan Section) Phase 2, Uyugan, Batanes24BA0017Flood control | 100% | September 9, 2024 | August 26, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: March 4, 2024 · Source fetched October 21, 2026
Rule Definition
Title similarity + distance or shared coordinates within municipality.
Triggering Data & citations
Similar project description near another contract in the same municipality
{
"contractId": "24BA0017",
"fundingYear": 2024,
"municipality": "UYUGAN (BATANES)",
"distanceMeters": 72.26379888769665,
"titleSimilarity": 0.9558031734712069
}Source documents
Possible Innocent Explanations
- Phased construction seasons
- Upstream/downstream segments recorded separately