Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24CC0293 (₱77.20M) is recorded as completed in 69 days against 239 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.5%. The contractor may have deployed unusually large resources or worked in parallel to finish ahead of schedule.

Public record entityConstruction of Reinforced Concrete Flood Control Structure, Barangay Cambaog (Sitio Teodoro), Bustos, Bulacan
LocationBUSTOS (BULACAN), BULACAN, Region IIIContract 24CC0293
Amount₱77,199,023.96 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Reinforced Concrete Flood Control Structure, Barangay Cambaog (Sitio Teodoro), Bustos, Bulacan24CC0293Flood control100%December 11, 2024June 24, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: April 16, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-04-16T00:00:00.000Z",
  "contractId": "24CC0293",
  "actualEndDate": "2024-06-24T00:00:00.000Z",
  "targetEndDate": "2024-12-10T00:00:00.000Z",
  "contractCostPhp": 77199023.96
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)BulacanBustosCambaog
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Kajiki 2025Man-Yi 2024
Hazard exposure
Active fault29.0 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)highUP NOAH Center / DOST-PAGASA (Project NOAH)LandslidehighUP NOAH Center / UP NIGS (Project NOAH)Storm surgenot inundated even at SSA4 (>5 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.