Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24A00165 (₱49.50M) is recorded as completed in 68 days against 173 planned; similar-cost projects take a median of 239 days, putting it in the fastest 1.9%. The contractor may have deployed extra resources or worked in favorable conditions, allowing for faster completion.

Public record entityRehabilitation of Flood Control Structure, Aringay River Basin, Barangay San Antonio, Aringay, La Union
LocationARINGAY (LA UNION), LA UNION, Region IContract 24A00165
Amount₱49,499,698.64 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Rehabilitation of Flood Control Structure, Aringay River Basin, Barangay San Antonio, Aringay, La Union24A00165Flood control100%September 28, 2024June 15, 2024—completedsumbong source

Start: April 8, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-04-08T00:00:00.000Z",
  "contractId": "24A00165",
  "actualEndDate": "2024-06-15T00:00:00.000Z",
  "targetEndDate": "2024-09-27T00:00:00.000Z",
  "contractCostPhp": 49499698.64
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo