| Year | Infra awards | Infra value | Goods & services | G&S value |
|---|---|---|---|---|
| 2020 | 1 | ₱6,569,355.02 | 3 | ₱5,441,787.15 |
| 2019 | 5 | ₱21,505,120.34 | 54 | ₱184,691,648.95 |
| 2018 | 5 | ₱18,267,241.92 | 103 | ₱128,002,037.88 |
| 2017 | 1 | ₱71,929,954.15 | 64 | ₱54,378,527.88 |
| 2016 | 0 | No awards that year | 60 | ₱28,702,216.89 |
| 2015 | 0 | No awards that year | 84 | ₱27,718,748.04 |
| 2014 | 0 | No awards that year | 53 | ₱22,922,960.02 |
| 2013 | 0 | No awards that year | 45 | ₱13,200,286.00 |
- Rehabilitation of Various Pumping Facilities
- Re-Piping and Installation of Pipelines at Various
- Repair of Damaged Road
- Proposed Reinforced Confinement Wall
- Item B Proposed STRB Remedial Works and Clearing
- Construction of a Mezzanine Floor on Baguio Water
- SLOPE PROTECTION
- DISTRIBUTION AND TRANSMISSION LINES
- RAINWATER HARVESTING FACILITY AT BUSOL WATERSHED
- SITE DEVELOPMENT
- Construction Of Steel (Aus-Aid) Tank at Camp 8 Pumping Station
- Construction
Source: PhilGEPS award notices (BetterGov.PH open mirror, CC0), dataset. Figures are award amounts as published by each procuring office, not payments or completed work. Coverage runs through late 2025; 2026 awards are not in the source yet. Award notices list no bidder counts or approved budgets (ABC), so those are not shown. These pages carry no automated flags.