MARIVELES MENTAL HOSPITAL
DOH hospital · Department of Health · 850 awards · ₱313,565,467.21
Totals by year
| Year | Infra awards | Infra value | Goods & services | G&S value |
|---|---|---|---|---|
| 2020 | 0 | — | 13 | ₱12,060,610.40 |
| 2019 | 4 | ₱20,003,757.05 | 175 | ₱56,383,780.62 |
| 2018 | 6 | ₱38,657,450.06 | 115 | ₱29,061,686.29 |
| 2017 | 4 | ₱5,032,950.77 | 83 | ₱54,725,763.00 |
| 2016 | 5 | ₱45,498,094.30 | 251 | ₱21,971,600.96 |
| 2015 | 1 | ₱486,930.74 | 32 | ₱3,374,487.20 |
| 2014 | 1 | ₱14,947,649.29 | 43 | ₱9,997,604.16 |
| 2013 | 0 | — | 117 | ₱1,363,102.37 |
- Upgrading of Electrical Transformer and Dist. Line
- Completion of Infirmary Building Phase II
- Completion of OPD and ACIU Building Phase II
- Existing Portion of Concrete Fence
- Construction of Canteen
- Conversion of Existing OPU to Central Records
- Construction of 3-Storey Infirmary Building Phase1
- Expansion od OPD & ACIU Building Phase II
- Materials-Improvement of Accessibility(BAC Office)
- Labor - Improvement of Accessibility(BAC Office)₱58,000.00· 2018-05-02· Other construction· V. COLLADO WELDING SHOP
- Materials and Labor for Installation₱44,400.00· 2017-07-24· Other construction· V. COLLADO WELDING SHOP
- Nego Proc Improvement of Dietary Cooking Area
- Re-Bidding Repair/Improvement of Laundry & Linen A
- Expansion of material Recovery Facility
- Expansion of Procurement and MMU Building
- Expansion of OPD & ACIU Building Phase-1
- Rehabilitatiobn and Improvement of OT Building
- Expansion of Male Ward
- Expansion of HOPSS Building
- Repair/Rehab on diff Bldg affected by typhoon
- Construction
Source: PhilGEPS award notices (BetterGov.PH open mirror, CC0), dataset. Figures are award amounts as published by each procuring office, not payments or completed work. Coverage runs through late 2025; 2026 awards are not in the source yet. Award notices list no bidder counts or approved budgets (ABC), so those are not shown. These pages carry no automated flags.