BARANGAY TENAN, IPIL, ZAMBOANGA SIBUGAY
Other office · Barangays and Sangguniang Kabataan · 23 awards · ₱4,925,007.98
Totals by year
| Year | Infra awards | Infra value | Goods & services | G&S value |
|---|---|---|---|---|
| 2025 | 7 | ₱1,076,807.50 | 1 | ₱78,100.00 |
| 2024 | 3 | ₱656,369.00 | 1 | ₱87,500.00 |
| 2023 | 6 | ₱1,570,430.44 | 0 | No awards that year |
| 2022 | 2 | ₱318,951.04 | 1 | ₱998,000.00 |
| 2021 | 0 | No awards that year | 1 | ₱68,050.00 |
| 2020 | 0 | No awards that year | 1 | ₱70,800.00 |
- IMPROVEMENT OF BARANGAY COVERED COURT (Direct Contracting Proprietary in Nature)
- CONSTRUCTION OF CONCRETE PATHWAY GOING TO MOSQUE (PRK GEMELINA) (Direct Contracting Proprietary in Nature)
- IMPROVEMENT OF MULTI-PURPOSE BUILDING (Direct Contracting Proprietary in Nature)
- CONSTRUCTION OF LEARNING CENTER (Direct Contracting Proprietary in Nature)
- CONSTRUCTION OF WAITING SHED (Direct Contracting Proprietary in Nature)
- ROAD GRAVELLING (Direct Contracting Proprietary in Nature)
- CONSTRUCTION OF MULTI PURPOSE HALL PHASE 1 (Direct Contracting Proprietary in Nature)
- REHABILITATION OF MADRASAH BUILDING (Direct Contracting Proprietary in Nature)
- CONSTRUCTION OF PATHWAY (Direct Contracting Proprietary in Nature)
- CONSTRUCTION OF OPEN COURT (Direct Contracting Proprietary in Nature)
- Construction of pathway (Direct Contracting Proprietary in Nature)
- Installation of solar street lights (Direct Contracting Proprietary in Nature)
- Installation of solar street lights (Direct Contracting Proprietary in Nature)
- Installation of solar street lights (Direct Contracting Proprietary in Nature)
- Road concreting phase 3 (Direct Contracting Proprietary in Nature)
- Installation of solar street lights (Direct Contracting Proprietary in Nature)
- Road concreting phase 2 (Direct Contracting Proprietary in Nature)
- Installation of Water System (Direct Contracting Proprietary in Nature)
Source: PhilGEPS award notices (BetterGov.PH open mirror, CC0), dataset. Figures are award amounts as published by each procuring office, not payments or completed work. Coverage runs through late 2025; 2026 awards are not in the source yet. Award notices list no bidder counts or approved budgets (ABC), so those are not shown. These pages carry no automated flags.