Construction of Yawa River Control System
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ALBAY 2ND DEO (DPWH) awarded ₱65,244,599.62 to NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION/3RB CONSTRUCTION & SUPPLY (JOINT VENTURE) on 2022-02-17, per PhilGEPS.
- Amount awarded
- ₱65,244,599.62
- Award date
- 2022-02-17
- Awardee
- NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION/3RB CONSTRUCTION & SUPPLY (JOINT VENTURE)
- Procuring office
- DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ALBAY 2ND DEO (Other office)
- Category
- Infrastructure · Other construction
- PhilGEPS business category
- Construction Projects
- Area of delivery
- Albay
- Reference no.
- 22FB0109
- Contract no.
- 22FB0109
- Notice title
- OO2 - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Yawa River Control System (Legazpi City Urban Drainage), Legazpi City
Context
In 2022, this office published 292 awards of the same type (Other construction); the median amount was ₱38,438,386.70.
A computed comparison only. It is not an indicator or finding.
Source: PhilGEPS award notices (BetterGov.PH open mirror, CC0). Dataset file · version bettergovph/philgeps-data@b98de579579e8c7e79bac2a22ac7491549db6d0d (lastModified 2026-01-06) · retrieved 2026-10-22 · row 73ef489a-6842-4c67-801c-10f947670f92.
Award notices do not list bidder counts or the approved budget for the contract (ABC), so neither is shown. Amounts are as awarded, not as paid. Named offices and awardees may reply or request a correction.