CONSTRUCTION OF SIDEWALK W/ CURB & GUTTER & CANAL

MUNICIPALITY OF ESTANCIA, ILOILO (Municipality of Estancia, Iloilo) awarded ₱791,913.40 to WOODLAND CONSTRUCTION AND SUPPLY INC on 2023-08-24, per PhilGEPS.

Amount awarded
₱791,913.40
Award date
2023-08-24
Awardee
WOODLAND CONSTRUCTION AND SUPPLY INC
Procuring office
MUNICIPALITY OF ESTANCIA, ILOILO (Central office)
Agency
Municipality of Estancia, Iloilo
Category
Infrastructure · Other construction
PhilGEPS business category
Construction Projects
Area of delivery
Iloilo
Reference no.
2023-024
Contract no.
2023-024
Notice title
CONSTRUCTION OF SIDEWALK W/ CURB & GUTTER & CANAL (Phase 1)

Context

In 2023, this office published 10 awards of the same type (Other construction); the median amount was ₱994,281.02.

A computed comparison only. It is not an indicator or finding.