← MUNICIPALITY OF IBA, ZAMBALES

DREDGING AND DESILTING OF 1,740.0 L.M. BALIN BOCBO

MUNICIPALITY OF IBA, ZAMBALES (Municipality of Iba, Zambales) awarded ₱8,983,475.66 to G.M.R. CONSTRUCTION AND SUPPLY on 2019-09-23, per PhilGEPS.

Amount awarded
₱8,983,475.66
Award date
2019-09-23
Awardee
G.M.R. CONSTRUCTION AND SUPPLY
Procuring office
MUNICIPALITY OF IBA, ZAMBALES (Central office)
Agency
Municipality of Iba, Zambales
Category
Infrastructure · Other construction
PhilGEPS business category
Construction Projects
Area of delivery
Zambales
Reference no.
CI2019-008
Contract no.
CI2019-008
Notice title
DREDGING AND DESILTING OF 1,740.0 L.M. BALIN BOCBOC RIVER PHASE I (BEGINNING AT 300.0 L.M. DOWNSTREAM SIDE OF DAMPAY-AMUNGAN BRIDGE TO BALIN BOCBOC BRIDGE SAN AGUSTIN)

Context

In 2019, this office published 25 awards of the same type (Other construction); the median amount was ₱2,723,435.55.

A computed comparison only. It is not an indicator or finding.

Source: PhilGEPS award notices (BetterGov.PH open mirror, CC0). Dataset file · version bettergovph/philgeps-data@b98de579579e8c7e79bac2a22ac7491549db6d0d (lastModified 2026-01-06) · retrieved 2026-10-22 · row c4edcf3a-dcd7-48ae-9507-7455b49d97d0.

Award notices do not list bidder counts or the approved budget for the contract (ABC), so neither is shown. Amounts are as awarded, not as paid. Named offices and awardees may reply or request a correction.