Buildings and Facilities20JC0056

CONSTRUCTION OF COVERED COURT IN FRONT OF TANGHALAN NG PARAISO, BRGY. POBLACION, SIOCON, ZAMBOANGA DEL NORTE

CONSTRUCTION OF COVERED COURT IN FRONT OF TANGHALAN NG PARAISO, BRGY. POBLACION, SIOCON, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱4,925,146.87. Status: Reported complete (DPWH). Contractor on record: BORGONIA CONST AND ENT. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Box Culvert, Owaon, Dapitan City, Zamboanga del Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-20-0004325

₱78,265,000.00 · FY2020

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,925,146.87

Progress

Reported complete (DPWH)

Start Date

October 25, 2020

Target End

April 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.