Buildings and Facilities19HH0242

CONSTRUCTION OF MULTI PURPOSE BUILDING AT VICENTE SOTTO MEMORIAL MEDICAL CENTER (PHASE 2), BRGY. SAMBAG II, CEBU CITY

CONSTRUCTION OF MULTI PURPOSE BUILDING AT VICENTE SOTTO MEMORIAL MEDICAL CENTER (PHASE 2), BRGY. SAMBAG II, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱45,879,999.92. Status: Reported complete (DPWH). Contractor on record: JAMARI CONST FORMERLY FRAE CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-19-0011181

₱6,992,000.00 · FY2019

Released to Regional Science High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

88 projects · ₱2.2B total · 0 flags

4. Implementation

Contract Amount

₱45,879,999.92

Progress

Reported complete (DPWH)

Start Date

January 17, 2020

Target End

November 11, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.