Roads25DC0086

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY GULO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY GULO is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱14,327,448.00. Status: Past target date (DPWH On-Going). Contractor on record: ARCEGA ACUZAR CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROI-25-0008577 · ₱372,885 · release to the district office, not itemized per project

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25DC0086 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    27% reported · imagery 2022-12-07 → 2025-10-06

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY GULO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in the City of Calaca, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-25-0008577

₱372,885.00 · FY2025

Released to Ilocos Training and Regional Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

14 projects · ₱211.9M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (MULTI-PURPOSE CONVENTION/SPORTS COMPLEX), TANAUAN CITY, BATANGAS

Batangas 3rd DEO, Region IV-A

2024₱19.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. PARANG, MARIKINA CITY

Metro Manila 1st DEO, National Capital Region

2024₱19.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, HQS, AIR, LEGASPI COMPOUND, FORT ANDRES BONIFACIO, TAGUIG CITY, PHASE III

National Capital Region, National Capital Region

2025₱18.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (EASTERN POLICE DISTRICT) BRGY. CORAZON DE JESUS, SAN JUAN CITY PACKAGE VII

Metro Manila 1st DEO, National Capital Region

2024₱14.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY TUM

Batangas 3rd DEO, Region IV-A

2025₱14.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT SAN PIOQUINTO

Batangas 3rd DEO, Region IV-A

2025₱14.3M
Past target date (DPWH On-Going)
View all 14 projects →

4. Implementation

Contract Amount

₱14,327,448.00

Progress

Past target date (DPWH On-Going)

Start Date

May 29, 2025

Target End

December 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)BatangasLaurelGulod
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.