Roads20KJ0016

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TANGUB-BONIFACIO BYPASS ROAD (PISAAN-BUENAVISTA SECTION) MISAMIS OCCIDENTAL

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TANGUB-BONIFACIO BYPASS ROAD (PISAAN-BUENAVISTA SECTION) MISAMIS OCCIDENTAL is a DPWH-tracked public work in Misamis Occidental 2nd DEO, Region X. Reported contract value: ₱68,756,055.04. Status: Reported complete (DPWH). Contractor on record: MINDANAO ROCK. Figures trace to dpwh.

Misamis Occidental 2nd DEO, Region X
Region: Region X

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱100,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXI-20-0011845 · ₱970,348 · release to the district office, not itemized per project

    Possible match · score 0.66

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20KJ0016 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-08-30 → 2025-03-12

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TANGUB-BONIFACIO BYPASS ROAD (PISAAN-BUENAVISTA SECTION) MISAMIS OCCIDENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Usugan River Flood Control Project (Downstream), Package A, Bonifacio, Misamis Occidental
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-20-0011845

₱970,348.00 · FY2020

Released to Davao del Norte State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱68,756,055.04

Progress

Reported complete (DPWH)

Start Date

December 2, 2020

Target End

August 27, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region X (Northern Mindanao)Misamis OccidentalBonifacioPisa-an
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.