Buildings and Facilities23GM0039

CONSTRUCTION OF MULTI-PURPOSE BUILDING - COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BULWANGAN, HINOBA-AN, NEGROS OCCIDENTAL

CONSTRUCTION OF MULTI-PURPOSE BUILDING - COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BULWANGAN, HINOBA-AN, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 3rd DEO, Negros Island Region. Reported contract value: ₱1,903,025.20. Status: Reported complete (DPWH). Contractor on record: DURABUILD CONST. Figures trace to dpwh.

Negros Occidental 3rd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure (Irrigation), Barangay Luna, Cadiz City, Negros Occidental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0027182

₱1,099,005.00 · FY2023

Released to Philippine Merchant Marine Academy (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,903,025.20

Progress

Reported complete (DPWH)

Start Date

April 20, 2023

Target End

June 18, 2023

5. Audit