Roads24OD0034

CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, PHASE 4, PKG 8, BARANGAY 176, CALOOCAN CITY

CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, PHASE 4, PKG 8, BARANGAY 176, CALOOCAN CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱7,799,930.40. Status: Reported complete (DPWH). Contractor on record: IM CONST CORP. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-E-24-0005592 · · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱7,799,930 · I.M CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-12-04 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, PHASE 4, PKG 8, BARANGAY 176, CALOOCAN CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Banks of Creeks, Barangay 166, ( Phase 3 ) , Caloocan City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-24-0005592

₱0.00 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24OD0034

₱7,799,930.40 · I.M CONSTRUCTION

Award / contract ref: 24OD0034

Contractor

B

304 projects · ₱10.7B total · 6 flags

4. Implementation

Contract Amount

₱7,799,930.40

Progress

Reported complete (DPWH)

Start Date

February 14, 2024

Target End

July 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of CaloocanBarangay 171
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.