Water Provision and Storage23F00189

CLUSTER VII-CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-VII-I-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, PRIETO DIAZ, SORSOGON; VII-II-CONSTRUC

CLUSTER VII-CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-VII-I-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, PRIETO DIAZ, SORSOGON; VII-II-CONSTRUC is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱19,299,530.96. Status: Reported complete (DPWH). Contractor on record: AC8 BUILDERS. Figures trace to dpwh.

Region V, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23F00189 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-06-20 → 2022-06-20

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CLUSTER VII-CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-VII-I-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, PRIETO DIAZ, SORSOGON; VII-II-CONSTRUC

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

7 projects · ₱71.6M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, LAGONOY, CAMARINES SUR, BINANUAHAN, STA. MARIA, PINAMIGA

Region V, Region V

2023₱28.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II AT BRGY. BACOLOD (POBLACION), IROSIN, SORSOGON, IROSIN, SORSOGON (2ND LEGISLATIVE DI

Region V, Region V

2023₱4.9M
Reported complete (DPWH)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. DIVINA PASTORA, BATO, CAMARINES SUR

Camarines Sur 5th DEO, Region V

2023₱4.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II AT BARANGAY CAGBUNGA, PAMPLONA, CAMARINES SUR, CAGBUNGA, PAMPLONA, CAMARINES SUR (2N

Region V, Region V

2023₱4.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II AT BRGY. TINANGQUIHAN (ZONE 6), LIBMANAN, CAMARINES SUR, TINANGQUIHAN, LIBMANAN,

Region V, Region V

2023₱4.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II AT BARANGAY ODICON, PASACAO, CAMARINES SUR, ODICON, PASACAO, CAMARINES SUR (2ND LEGI

Region V, Region V

2023₱4.8M
Past target date (DPWH On-Going)
View all 7 projects →

4. Implementation

Contract Amount

₱19,299,530.96

Progress

Reported complete (DPWH)

Start Date

August 16, 2023

Target End

March 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)SorsogonPrieto DiazCarayat
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.