GAA 2016 MFO-216JA0060

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BUSUGAN RIVER, SINUBUNG SECTION, (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY 1ST LD

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BUSUGAN RIVER, SINUBUNG SECTION, (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY 1ST LD is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱18,520,404.48. Status: Reported complete (DPWH). Contractor on record: ED1SON DEVELOPMENT. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control structure, Busugan River, Sinubung Section, (including Right of Way Acquisition), Zamboanga City 1st LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-16-0035183

₱2,982,261.00 · FY2016

Released to Regional Office - X (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱18,520,404.48

Progress

Reported complete (DPWH)

Start Date

March 30, 2016

Target End

May 13, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.