REHABILITATION/ CONCRETING OF PUROK 2 TO PUROK 7 FMR, BRGY. ZILLOVIA, TALACOGON, AGUSAN DEL SUR
REHABILITATION/CONCRETING OF PUROK 2 TO PUROK 7 FMR, BRGY. ZILLOVIA, TALACOGON, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱24,874,902.78. Status: Reported complete (DPWH). Contractor on record: DATREBIL CONST. Figures trace to dpwh.
DPWH did not publish coordinates for this project. Location estimated from the project title (barangay level); satellite images may not show the exact site.
Total Contract Cost