Buildings and Facilities23GN0026

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CAMBARUS, PONTEVEDRA, NEGROS OCCIDENTAL

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CAMBARUS, PONTEVEDRA, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱4,898,013.54. Status: Reported complete (DPWH). Contractor on record: ONE TERRA BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱5,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱4,898,014 · ONE TERRA BUILDERS AND CONSTRUCTION SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-01-21 → 2025-08-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CAMBARUS, PONTEVEDRA, NEGROS OCCIDENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure (Irrigation), Barangay Luna, Cadiz City, Negros Occidental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Negros Occidental 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23GN0026 - Construction of Multi-Purpose Building,

₱4,898,013.54 · ONE TERRA BUILDERS AND CONSTRUCTION SUPPLY

Award / contract ref: 23GN0026

Contractor

A

86 projects · ₱664.8M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - JCT. PONTEVEDRA - LA CASTELLANA ROAD - K0046+000 - K0047+500

Negros Occidental 4th DEO, Negros Island Region

2024₱53.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0042+600 - K0045+862, K0045+920 - K0045+962

Negros Occidental 4th DEO, Negros Island Region

2024₱30.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION RECONSTRUCTION UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - JCT. PONTEVEDRA-LA CASTELLANA ROAD, K0045+(-975) -K0045+436, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2020₱26.1M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0040+(-664) - K0040+575, K0040+585 - K0041+230, K0041+272 - K0042+600

Negros Occidental 4th DEO, Negros Island Region

2025₱25.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REINFORCED CONCRETE DECK GIRDER (RCDG) BRIDGE INCLUDING APPROACHES AND SIDE SLOPE PROTECTION AT BRGY. CANROMA TO SITIO SUA TRINIDAD ROAD, BRGY. DON SALVADOR BENEDICTO, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2023₱24.7M
Reported complete (DPWH)
No sat.

RECONSTRUCTION TO CONCRETE PAVEMENT - JCT. PONTEVEDRA - LA CASTELLANA ROAD, K0045+436 - K0046+545, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2021₱21.7M
Reported complete (DPWH)
View all 86 projects →

4. Implementation

Contract Amount

₱4,898,013.54

Progress

Reported complete (DPWH)

Start Date

February 13, 2023

Target End

June 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Negros Island Region (NIR)Negros OccidentalCity of BagoLag-Asan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.