Roads20BH0082

CONCRETING OF BRGY. ROAD IN BRGY. RIZAL TO GUD

CONCRETING OF BRGY. ROAD IN BRGY. RIZAL TO GUD is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: CAMBERWELL CONST AND SUPPLIES. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱41,652 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20BH0082 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-02-04 → 2025-06-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF BRGY. ROAD IN BRGY. RIZAL TO GUD

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱41,652,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dabubu Grande-Salay Flood Control, San Agustin, Isabela
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Isabela 4th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

237 projects · ₱3.3B total · 5 flags

Other projects by this contractor

Construction of Bongabong River Control, Brgy. Morente Section, Bongabong, Oriental Mindoro

BONGABONG (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱96.5M
Reported complete (DPWH)

Construction of Cagayan River Flood Control Project, Barangay Furao, Gamu, Isabela

GAMU (ISABELA), ISABELA, Region II

2024₱96.5M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF PINACANAUAN RIVER FLOOD CONTROL STRUCTURE, BRGY. DICAMAY,

Isabela 3rd DEO, Region II

2025₱96.4M
Reported complete (100% progress, DPWH status On-Going)

Construction of Cagayan River Flood Control Project, Barangay Magsaysay, Naguilian, Isabela, Phase II

SAN MARIANO (ISABELA), ISABELA, Region II

2024₱96.4M
Reported complete (DPWH)

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT BARANGAY PALATTAO (CONTINUATION), NAGUILIAN

Isabela 3rd DEO, Region II

2025₱96.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCES ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - ACCESS ROAD LEADING TO PALANAN AIRPORT, PALANAN, ISABELA

Isabela 3rd DEO, Region II

2021₱96.3M
Reported complete (DPWH)
View all 237 projects →

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

September 9, 2020

Target End

December 19, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)IsabelaSan IsidroRizal East
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Dry conditions likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.