Roads16BK0128

REPAIR/RESTORATION/IMPROVEMENT OF JCT. VICTORIA-MADDELA-ALICIA-KASIBU ROAD (S04748LZ), K0382+079-K0382+097, JOSE ANCHETA, MADDELA, QUIRINO

REPAIR/RESTORATION/IMPROVEMENT OF JCT. VICTORIA-MADDELA-ALICIA-KASIBU ROAD (S04748LZ), K0382+079-K0382+097, JOSE ANCHETA, MADDELA, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱2,639,127.36. Status: Reported complete (DPWH). Contractor on record: C-BROS CONST. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-ROVIII-16-0004539 · ₱560,000 · release to the district office, not itemized per project

    Possible match · score 0.77

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 16BK0128 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2012-04-25 → 2025-06-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REPAIR/RESTORATION/IMPROVEMENT OF JCT. VICTORIA-MADDELA-ALICIA-KASIBU ROAD (S04748LZ), K0382+079-K0382+097, JOSE ANCHETA, MADDELA, QUIRINO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0004539

₱560,000.00 · FY2016

Released to Southern Samar National Comprehensive High ScPS re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

106 projects · ₱1.2B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - ARITAO-QUIRINO ROAD (UMASOK BR. AND APPROACHES), PACKAGE 2, QUIRINO

Region II, Region II

2024₱144.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - AGUINALDO - TOBOY - NATONIN ROADAGUINALDO IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2022₱118.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BANAUE - MAYOYAO - A. LISTA - ISABELA BDRY ROAD, KO341+(-880) - KO341+(-252), KO341+(-069) - KO348+187

Cordillera Administrative Region, Cordillera Administrative Region

2020₱116.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS BANAUE - HUNGDUAN - BENGUET BDRY ROAD, KO407+480 - KO

Cordillera Administrative Region, Cordillera Administrative Region

2021₱114.1M
Reported complete (DPWH)
No sat.

BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - DUMABATO BR. (B04453LZ) ALONG DUMABATO-BALLIGUI RD, MADDELA, QUIRINO

Quirino DEO, Region II

2023₱96.5M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES ALONG NUEVA VIZCAYA-IFUGAO-MT. PROVINCE ROAD, KO296+000,KO296+1038-KO297+210,KO301+807-KO301+917,KO307+698,KO320+545-KO320+605,KO322+632,KO332+377-KO332+407,KO333+18

Ifugao 1st DEO, Cordillera Administrative Region

2020₱72.0M
Reported complete (DPWH)
View all 106 projects →

4. Implementation

Contract Amount

₱2,639,127.36

Progress

Reported complete (DPWH)

Start Date

January 4, 2017

Target End

March 5, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)QuirinoMaddelaJose Ancheta
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.