Buildings and Facilities15JD0061

CONSTRUCTION OF COVERED COURT BRGY. SAN JOSE, SERGIO OSMEÑA, ZAMBOANGA DEL NORTE

CONSTRUCTION OF COVERED COURT BRGY. SAN JOSE, SERGIO OSMEÑA, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱1,901,061.18. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2016 · ₱15,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVIII-16-0009922 · ₱8,295,800 · release to the district office, not itemized per project

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱1,901,061 · RUDHIL CONSTRUCTION & ENTERPRISES, .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2012-08-09 → 2025-06-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF COVERED COURT BRGY. SAN JOSE, SERGIO OSMEÑA, ZAMBOANGA DEL NORTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Extension of Flood Control Structure along the Right Bank of Piao River (Downstream) Brgy. Lawis, Sindangan, Zamboanga del Norte
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0009922

₱8,295,800.00 · FY2016

Released to Visayas State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Projects

₱1,901,061.18 · RUDHIL CONSTRUCTION & ENTERPRISES, .

Award / contract ref: C-15JD0061

Contractor

B

1,028 projects · ₱22.5B total · 0 flags

4. Implementation

Contract Amount

₱1,901,061.18

Progress

Reported complete (DPWH)

Start Date

January 19, 2016

Target End

March 18, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IX (Zamboanga Peninsula)Zamboanga del NorteSergio Osmeña Sr.San Jose
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.