Buildings and Facilities24LI0089

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE I) BARANGAY POBLACION, MONKAYO, DAVAO DE ORO

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE I) BARANGAY POBLACION, MONKAYO, DAVAO DE ORO is a DPWH-tracked public work in Davao de Oro 2nd DEO, Region XI. Reported contract value: ₱29,598,981.62. Status: Past target date (DPWH On-Going). Contractor on record: DISEM CONST AND SUPPLY. Figures trace to dpwh.

Davao de Oro 2nd DEO, Region XI
Region: Region XI

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24LI0089 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    34% reported · imagery 2018-11-22 → 2025-07-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE I) BARANGAY POBLACION, MONKAYO, DAVAO DE ORO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Mamunga Creek leading to Agusan River, Barangay Mamunga, Monkayo, Davao de Oro
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Davao de Oro 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

163 projects · ₱2.2B total · 1 flags

4. Implementation

Contract Amount

₱29,598,981.62

Progress

Past target date (DPWH On-Going)

Start Date

April 29, 2024

Target End

January 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region XI (Davao Region)Davao de OroMonkayoPoblacion
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.