GAA 2016 MFO-115K00244

ROAD UPGRADING(UNPAVED TO PAVED) BASED ON GRS,TRAFFIC BM FOR UPGRADING TO PRS(HDM-4)JCT.MARADUGAO-CA

ROAD UPGRADING(UNPAVED TO PAVED) BASED ON GRS,TRAFFIC BM FOR UPGRADING TO PRS(HDM-4)JCT.MARADUGAO-CA is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱80,425,774.01. Status: Reported complete (DPWH). Contractor on record: C'ZARLES CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱80,425,774.01

Progress

Reported complete (DPWH)

Start Date

February 26, 2016

Target End

July 20, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.