Flood Control and Drainage17HH0025No coordinates published by DPWH

CONSTRUCTION / MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AT BRGY. BUSAY, CEBU CITY

CONSTRUCTION / MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AT BRGY. BUSAY, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: ON POINT CONST AND DEVELOPMENT CORP FORMERLY:ON POINT CONST. Figures trace to dpwh.

Cebu City DEO, Region VII

DPWH did not publish coordinates for this project. Location estimated from the project title (barangay level); satellite images may not show the exact site.

Region: Region VII

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱50,000

    Probable match · score 0.93

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-D-17-0022755 · ₱2,108,129 · release to the district office, not itemized per project

    Possible match · score 0.71

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱45,014,807 · UKC BUILDERS, . / ON POINT CONSTRUCTION JOINT VENTURE

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-05-15 → 2025-01-18

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION / MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AT BRGY. BUSAY, CEBU CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Maintenance of Flood Control Mitigation Structures at Brgy. Busay, Cebu City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0022755

₱2,108,129.00 · FY2017

Released to Philippine Air For ( Air Forces ) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction / Maintenance of Flood Control Mitiga

₱45,014,807.48 · UKC BUILDERS, . / ON POINT CONSTRUCTION JOINT VENTURE

Contractor

C

41 projects · ₱1.6B total · 1 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAHIGA CREEK, PHASE 3, BARANGAY S

Cebu 6th DEO, Region VII

2025₱122.4M
Past target date (DPWH On-Going)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROAD UNDER CANSAGA BAY BRIDGE (MANDAUE SIDE) BRGY. P

Cebu 6th DEO, Region VII

2023₱98.9M
Reported complete (DPWH)

002: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BUTUANON RIVER, BARANGAY CASUNTINGAN TO BARANGAY CABANCALAN (PHASE IV), MANDAUE CITY, CEBU

Cebu 6th DEO, Region VII

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SEGMENT 2, BARANGAY HILAAN, BONTOC, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY JAGOBIAO, MANDAUE CITY, CEBU

Cebu 6th DEO, Region VII

2025₱77.1M
Past target date (DPWH On-Going)
No sat.

Construction of Flood Control Structure along Butuanon River (Downstream) Outfall, Barangay Pakna-an, Mandaue City, Cebu

MANDAUE CITY (CEBU), CEBU, Region VII

2025₱72.3M
Reported complete (DPWH)
View all 41 projects →

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

March 24, 2017

Target End

November 27, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)City of Cebu
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Active faultLandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.