Construction of Drainage Structure22LA0119

Construction (Completion) of Drainage, Purok Marang, Pindasan, Mabini, Davao de Oro

Construction (Completion) of Drainage, Purok Marang, Pindasan, Mabini, Davao de Oro is a DPWH-tracked public work in MABINI (DOÑA ALICIA) (DAVAO DE ORO), DAVAO DE ORO, Region XI. Reported contract value: ₱2,939,999.89. Status: Reported complete (DPWH). Contractor on record: TWO DEGREES CONST AND SUPPLY. Figures trace to sumbong.

MABINI (DOÑA ALICIA) (DAVAO DE ORO), DAVAO DE ORO, Region XI
Region: Region XI

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱5,000

    Probable match · score 0.89

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-22-0003152 · ₱756,564,000

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22LA0119 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-07-24 → 2025-10-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Davao de Oro

Based on the coordinates published with the DPWH record and NOAH file Compostella Valley.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Construction (Completion) of Drainage, Purok Marang, Pindasan, Mabini, Davao de Oro

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Drainage Del Pilar, Mabini, Davao de Oro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003152

₱756,564,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002642

₱535,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002791

₱62,400,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002783

₱45,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006775

₱37,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,939,999.89

Progress

Reported complete (DPWH)

Start Date

March 29, 2022

Target End

July 8, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region XI (Davao Region)Davao de OroMabiniPindasan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.