GAA 2025 SSP25KH0045

REHABILITATION OF ROADS IN BARANGAY PAGATPAT, CAGAYAN DE ORO CITY

REHABILITATION OF ROADS IN BARANGAY PAGATPAT, CAGAYAN DE ORO CITY is a DPWH-tracked public work in Cagayan de Oro City 1st DEO, Region X. Reported contract value: ₱9,837,769.48. Status: Past target date (DPWH On-Going). Contractor on record: CAGALAWAN ENT INC. Figures trace to dpwh.

Cagayan de Oro City 1st DEO, Region X
Region: Region X

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱4,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25KH0045 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    90% reported · imagery 2022-10-31 → 2025-11-12

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION OF ROADS IN BARANGAY PAGATPAT, CAGAYAN DE ORO CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱4,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Cagayan de Oro River (Revetment 2), Balulang, Cagayan de Oro City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cagayan de Oro City 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

118 projects · ₱1.2B total · 0 flags

4. Implementation

Contract Amount

₱9,837,769.48

Progress

Past target date (DPWH On-Going)

Start Date

May 16, 2025

Target End

October 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region X (Northern Mindanao)City of Cagayan De OroPagatpat
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.