Roads25GD0010

CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CULILANG, PRESIDENT ROXAS, CAPIZ

CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CULILANG, PRESIDENT ROXAS, CAPIZ is a DPWH-tracked public work in Capiz 1st DEO, Region VI. Reported contract value: ₱4,949,644.47. Status: Past target date (DPWH On-Going). Contractor on record: WORKAVENUE INC. Figures trace to dpwh.

Capiz 1st DEO, Region VI
Region: Region VI

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱4,949,644 · WORKAVENUE INC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    83% reported · imagery 2016-03-17 → 2025-10-31

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CULILANG, PRESIDENT ROXAS, CAPIZ

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Facilities (Sea Wall) along Visayan Sea, Barangay Punta Cogon, Roxas City, Capiz
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Capiz 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,949,644.47

Progress

Past target date (DPWH On-Going)

Start Date

March 24, 2025

Target End

May 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VI (Western Visayas)CapizPresident RoxasCulilang
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Dry conditions likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.