Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22F00144 was awarded at 100.00% of its ABC. Across its 23 recorded contracts, HGG BUILDERS & SUPPLY was awarded at ≥99.5% of ABC 22 times (95.7%), versus 70.4% for flood-control contracts overall. It is possible that the winning bid simply matched the ABC exactly, which is allowed under procurement rules.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction/Improvement of Sipocot River Flood Mitigation Structures, Sipocot Camarines Sur22F00144Flood control | 100% | May 20, 2023 | May 20, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: June 27, 2022 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Camarines Sur 1st District Engineering Office",
"ratio": 1,
"abcPhp": 89101796.39,
"threshold": 0.995,
"contractId": "22F00144",
"contractor": "HGG BUILDERS & SUPPLY",
"contractCostPhp": 89101796.39
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate