Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 22FA0021 lists a cost of ₱59.40M, 2.59% above its Approved Budget for the Contract of ₱57.90M. Under RA 9184, awards normally may not exceed the ABC. This may be due to a data entry error or a subsequent approved variation not reflected in the ABC field.

Public record entityConstruction of Inabuyan Seawall, Barangay Alimsog, Sto. Domingo, Albay
LocationSANTO DOMINGO (LIBOG) (ALBAY), ALBAY, Region VContract 22FA0021
Amount₱59,400,000.00102.59% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Inabuyan Seawall, Barangay Alimsog, Sto. Domingo, Albay22FA0021Flood control100%October 11, 2022October 11, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: March 11, 2022 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Albay 1st District Engineering Office",
  "ratio": 1.0259068021960365,
  "abcPhp": 57899996.25,
  "threshold": 0.995,
  "contractId": "22FA0021",
  "contractor": "HI-TONE CONST & DEVELOPMENT CORP FORMERLY",
  "contractCostPhp": 59400000
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate
  • This may be due to a data entry error or a subsequent approved variation not reflected in the ABC field.

Cite this record

Love the Philippines. “Awards Very Close to the Budget Ceiling (C2): Construction of Inabuyan Seawall, Barangay Alimsog, Sto. Domingo, Albay.” Source: sumbong. Data as of October 21, 2026. https://lovethephilippines.com/risk/47844bff-5b19-4e74-9f96-389beb7e9e6a

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)AlbayGuinobatanBatbat
Storms whose wind field reached it
Nokaen 2026Fung-Wong 2025Fengshen 2025Bualoi 2025Man-Yi 2024
Hazard exposure
Active fault8.2 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)outside mapped flood zonesUP NOAH Center / DOST-PAGASA (Project NOAH)LandslidemediumUP NOAH Center / UP NIGS (Project NOAH)Storm surgenot inundated even at SSA4 (>5 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-11-03El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.